| > home > news |
News |
Bosley pumpout closed ufn
28 August 2010
Advice from BW on Friday 27 August 2010 says the the pump out
at Bosley top lock service block has suffered major mechanical failure
and parts cannot be obtained until after the Bank Holiday weekend.
The nearest pump outs to the south are at -
Heritage Marina just north of bridge 87;
Red Bull, on the Trent & Mersey
Canal.
The nearest pump outs to the north are at -
Macclesfield Canal Centre between bridges 38 and 37;
Bollington between bridges 28 and 27;
Higher Poynton north of bridge 15;
The junction of the
Ashton Canal & Huddersfield Narrow Canal.
|
Ramsdell Railings almost complete!
21
June 2010
A Macclesfield Canal Society working party has completed everything
that can presently be done to restore Ramsdell railings, between
bridges 76 and 77 at Scholar Green.
Alan, Sonia & Malcolm
worked at the railings on Sunday [20th June 2010]. They
now look splendid, as they are all painted bar the
five bays that are awaiting repair. But even more so as Paul Clegg
and two others have now strimmed a six foot swathe behind the
whole length of them. We tidied up, touching
up the paintwork and removing moss and grass
from the stones. There is also a sort of green fungus accumulating
on the white rails, but cleaning this off can wait. They
felt so encouraged, Malcolm sent a message to Paul, Terry and
David B (BW staff, see below) to thank them for this and the
other works. Paul said later that the more favourable comments
like this, then the more likely such works will be continued. The
other works are the continuation of vegetation clearance
southwards from Higher Poynton - they are now at Styperson
- and the painting of Br 78 at Congleton.
Malcolm has
now worked out the BW Manchester & Pennine (M&P) chain
of command on the Waterway and for the Macclesfield and
Trent & Mersey canals (M/T&M).
David Baldacchino
- Waterway Manager, M&P
Graham Lea - Maintenance Manager,
M&P
Wayne
Roome - Customer Service Supervisor, M/T&M
Terry Dale
- Construction Supervisor, M/T&M
Paul Clegg - Foreman,
M/T&M
Paul
is 'where it happens'. The society's further work
depends on how many theey can get for a working party and
how soon they can get the railings repaired. Details
on MCS meetings page.
|
Lock 4 sidepond reinstatement
12 April 2010
Malcolm, Stuart and John
loaded the re-furbished sidepond jackhead & baseplate onto
BW's float at Kerridge Dry Dock for Mike and Scott to take them
to Swettenham Street wharf, Macclesfield. They expected to be
at Bosley lock 4 on Monday April 12 to unload and fit them. The
rod and paddle fitting might be done in a stoppage in November. |
Major canal corridor upgrade proposed
17 March 2010
The
heavily used towpath through the Bollington area has been a cause
for concern this winter due to its extremely muddy condition. A group
met in Bollington in early March to consider putting together a project
to make improvements through the town. The attendees included Tim
Boddington and Malcolm Bower. Also attending were representatives
of Cheshire East Council, one of whom, Shea
O'Neill, managed the very successful
Weaver Way project.
Shea gave an excellent presentation on that project
and it's achievements. The Weaver Way in west Cheshire is about
20 miles long and of variable width up to several miles. The recreational
facilities throughout that area, but especially along the waterways,
have been significantly improved to great acclaim.
By the end of the meeting there was unanimous support for a proposal
to gain the interest of councillors and council officers in a major
project to undertake similar improvements in a corridor (yet to be
defined) running from Disley in the north east of the county, along
the Macclesfield canal to Red Bull, and down the Trent & Mersey
Canal to Middlewich, at which point it would meet the south end of
the Weaver Way project area. This would clearly be a long term project
taking several years to design, finance and execute.
Meanwhile Bollington still needs an early improvement to its towpath
and a limited project for that is being given further attention.
|
Bank improvements around Bollington
17 March 2010
Major
works are being carried out in the Bollington area to improve the
canal banks and stop a leak close to Adelphi mill. Bank reinforcement
has been completed between bridges 28 and 30. Blue Boar contractors
have used close spaced treated timber poles driven a metre into the
canal bed, draped with fabric and backfilled with dredgings for this
work (picture right).
A 150m length over Grimshaw Lane aqueduct, Bollington, has been
stanked off and drained to enable reconstruction of the wharf wall
at the north end of Adelphi mill and to investigate and stop a longstanding
slow leak in the same area (picture below with thanks to Mark Stedman).
 
Further works are being carried out north of Bollington, including
spot dredging at Whiteley Green (lower picture). The dredger pontoon
is 14ft wide and folds to enable passage through the bridges and
locks on this narrow canal. This, of course, requires bank access
in every length to be worked to get the digger on and off the pontoon.
|
Marple Wharf, redevelopment
10 January 2010
Joint statement from BW and Marple Civic
Society (MCS).
|
Vaudrey's Wharf remains at Risk!
12 October 2009
BW have stated that Vaudrey's Wharf continues to leak and if it
increases then they will stank it off. See
Vaudrey's Wharf page.
|
Bridge
26A, Clarence footbridge, a huge success!
29 August 2009, updated 17 March 2010
The long promised footbridge at Clarence Mill, Bollington, was
opened for use on 29th August 2009. It has proved to be an outstanding
success with a huge increase in the numbers of people visiting the
Café Waterside and
the Discovery
Centre. Café business
has more than doubled and visitors to the Discovery Centre have more
than trebled! Local residents are extremely happy that they can now
get straight onto the canal towpath. Plans are afoot to connect the
towpath directly with the Recreation Ground below the canal so that
children, in particular, can get to the recreation area from the
Clarence mill area without having to cross the main road under the
aqueduct. Full
details of the bridge on its own page.

|